Scope of Work
Design Assist Fire Alarm System
LEI was the design-assist contractor for the fire alarm system for over two years. LEI managed a crew averaging 10-15 electricians to complete the project. Working in cooperation with Ludvik Electric, Hensel Phelps Construction, The Denver Fire Department, SMG and APi Systems Group, LEI took an extremely complex project with a very aggressive schedule and broke it down into smaller manageable components to produce a high quality installation. Due to the nature of Fire Alarm Systems, LEI was required to interface with many different systems to include Smoke Control, Security and Electrical Power, which made the installation technically complex and unique.
Project Owner
City and County of Denver
Location
Project Dollar Value
$1,920,000
Project Start Date
January 2002
Project Finish Date
January 2005